|
| DSH 395. R; z% b8 N+ y0 ]! c% a
0 A3 H0 r& X+ s6 e4 C4 u | Separation of TNV-3 and SELV circuitry7 o0 a- J* I1 O# b( e1 `
| 2.3.2
# K& ^) g9 @" D2 Q; m _, }3 H- J | 60950(ed.3)+ O4 w- r/ _' o6 _
| 0 Y8 B( c0 j, Q0 T8 g
Standard(s):
. X) t3 ?% A5 j6 N: w5 N0 s! |IEC 60950 (1999) 3rd Ed.. M6 L) ~4 h$ x$ Z# D
Sub clause(s):* p2 I; B0 g. w& v$ C/ c
2.3.2
8 ?$ l; p8 C2 BSheet No.! e& [9 N% p6 K* n' J3 c0 o
395
% r3 @( ^8 C. Z6 l1 F2 LSubject:
1 X. _" i$ R! _& v! p; ^4 xSeparation of TNV –3 and SELV- K# n. J" b! D; o6 o
circuitry0 u. E4 `% v5 b6 ?' Y. L
Key words:7 f1 I% Y5 S! Z) x$ g% W$ T
- Separation of TNV-3 circuit
2 t5 u2 E8 _2 R, Z4 i9 X+ {6 Vand SELV circuit
6 Z& m$ z/ A# X$ K, H& WDecision taken at the 39th
, B4 b! H, [' Y1 S4 _* imeeting 20025 K/ Y( b, C* H: s, X5 V& M
Question:
) j. Q! L- |9 H9 P' M3 B' O1. Is it permitted to demonstrate that a TNV -3 circuit is adequately separated from a SELV circuit by
4 Q5 D9 C6 e6 o5 kmeans of single fault testing, in the situation where the spacings do not meet the requirements for basic
1 z& u: g M- Oinsulation? (The dielectric strength test is still required under Subclause 6.2.1.)
0 b+ Y6 k' G/ O) w" G# a2 f- R4 ]2. If so, is it required under the compliance paragraph to short circuit the insulation between the TNVcircuit' b+ i3 a9 L" ^+ _, w
and the SELV circuit at all points which do not meet the criteria for basic insulation, before6 ~: k. w/ j% t
carrying out the tests?0 w/ s3 S# x: t; t
3. If short circuiting the insulation before carrying out fault tests results in the equipment passing the tests,
4 l/ S8 M8 P$ C$ Ewhereas carrying out the fault tests without short circuiting the insulation would result in the equipment. W1 M3 _. H' o- e
failing the test, should the insulation be short circuited?- C+ L% b8 Z, f" B# g/ _9 b
Rationale:5 E5 ?- l9 `& J3 ^, Z6 ? z
1. Paragraph 1 of Sub-clause 2.3.2 requires that separation between a TNV-3 and a SELV circuit be such
# d" V* K4 g# _9 H1 H' othat in the event of a single fault, the SELV circuit remains below TNV-3 limits. Paragraph 2 of Subclause
; G5 R2 b1 }) m2.3.2 states that basic insulation will achieve this, but other solutions are not excluded. g6 @5 H' U) N: l1 X
Equipment is not required to meet either Paragraph 2 or 3. It can meet the single fault conditions stated' U5 v3 H, }4 G! h5 H
in Paragraph one and in the compliance paragraph.( u' R! |* O( e
2. According to the compliance paragraph, before carrying out the single fault tests, insulation which does7 m! {* |, c0 f3 o
not meet the requirements for basic insulation is short circuited. Presumably this does not mean that: }/ x+ j7 `# V* H8 t l d9 z
short circuits are to be applied between all tracks and components in the entire TNV-3 and SELV. {3 K: |1 S* T% M
circuitry which do not meet basic insulation, but that the insulation at the point where the TNV-3 circuit4 H! e8 w, `/ a0 a# \# q5 r' u( X
meets the SELV circuit is short-circuited.
5 V! K) d$ O3 d3. It is possible to envisage a situation where short circuiting the insulation between TNV-3 and SELV
5 s- d9 c& m2 x" P2 X" `could cause the TNV-3 voltages to be lowered. Fault tests under this condition would not represent the
% h# w ~: L) u6 Iworst case possible fault condition
4 I" A3 l# D2 q) Z6 A& Y) `: yDecision:
# i! E5 m: V0 C( A2 \6 _! j1. It is permitted to demonstrate compliance with Subclause 2.3.2 by means of single fault testing.* _. `8 u* p1 [# B' v
The limits in 2.3.1.b) shall not be exceeded in normal or single fault conditions.
$ J; h7 v+ k- @+ _* B; U2. Before carrying out single fault testing of components and insulation, insulation between TNV-3 and& o8 L p) V! W5 _
SELV circuits not meeting the requirements of Basic insulation should be short circuited if this results in
' Z$ A7 a2 i1 O ~ ]a worst case voltage measurement at accessible parts of SELV and TNV-1 circuits, and at accessible
" i4 i5 M# H4 D Y( Econductive parts during subsequent fault testing.+ P7 A* A5 t+ b( O5 T9 i0 ?
3. If the single fault test would be more severe if carried out without short circuiting the insulation, the test
( M0 I5 H& Y9 l) R3 Sshould be done without short circuiting the insulation.
( U. X( f4 k1 `: c) F; P( }' C# w" k# I- H
i. o% L: U4 x: b) v
|
本帖子中包含更多资源
您需要 登录 才可以下载或查看,没有帐号?注册安规
x
|